ETCS_chala:Layout 1 19/5/08 15:44 Page 1
ETCS
Keeping up-to-
date with ETCS
implementation
plans in Spain
This article aims to present the main aspects concerning the experience that the
development of the ERTMS system in Spain has produced. It will also describe the
established criteria for the migration to this new system.
Antonio Domínguez Chala,
The subjects that are going to be presented finished and in the reliability testing phase
Network Planning and
are as follows: before being entered into service.
Development Director, ADIF
a73
Implementation in the infrastructure The line Madrid-Segovia-Valladolid
a73
Implementation in the rolling stock (part of the future high-speed line from
a73
ERTMS migration strategy Madrid to northern Spain) is built with
a73
GSM-R implementation Thales and is in operation with Level 1 at
a73
STM status and perspective 300km/h. The same characteristics apply
a73
Compatibility between a SRS 2.3.0 to the line between Cordoba and Malaga,
train and SRS 2.2.2 Spanish trackside built by Dimetronic (Invensys).
a73
Conclusions Level 2 is available in all the lines as a
basic/main system and level 1 as a backup
Current ERTMS implementation in – except on the line between Zaragoza
the infrastructure and Huesca where only Level 1 is
High-Speed Network installed. Currently, trains are working
The actual development of the ETCS only with Level 1 because Level 2 is still in
system involves the trackside of the high- the verification and validation process.
speed lines and commuter lines. Delays have occurred due to the
The line between Madrid and incorporation into the RBCs of the
Barcelona is 650km and has been built Change Request 458.
by the company Ansaldo. Thales was used
for the line from Madrid to Lleida Conventional Network
(460km) and also the line from Lleida to In the conventional network, the line
Barcelona (190km). The installation of the between Albacete and La Encina (93km
system is completed and in operation in long), which forms part of the line
Level 1 at 300km/h. between Madrid and Valencia, is currently
The line between Zaragoza and Huesca undergoing tests, and has been the Pilot
incorporates Alstom technology and is also line developed in Spain within the TEN
66 EUROPEAN RAILWAY REVIEW
l
ISSUE 3
l
2008
Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116