rehfeld_banedanmark:Layout 1 20/5/08 10:56 Page 5
BANEDANMARK
We returned over three months in our working meetings
in the National Political Committee for Transport to this
priority discussion. Considering the political sensitivity of
such a change in priorities, our politicians bought in to the
model and have supported the result since.
Considering the challenges
Even though we have had a great success with changing the
way we work, there have been some challenges that we
didn’t entirely think through. It was our own and the
market’s ability to handle a threefold increase in production
in two years. These challenges are now surfacing, and some
of them include:
a73
The rail engineering market is limited and the abilities
have been liberalised and reduced substantially in the
past 10 years
a73
The rail constructor market has been liberalised.
Banedanmark’s own in-house construction company is
still the biggest player in the market
a73
Prices are very sensible to the activity in neighbouring
countries like Germany and Sweden
a73
We need to prove a 2% annual efficiency gain
a73
In 2014 the infrastructure backlog of 2006 must
be removed
a73
The operational budget was not increased proportionally
to the investment budget
In other words, the great challenge is to increase
efficiency with more or less the same workforce while
costs are rising.
And then there is signalling…
This article’s main objective has been to tell you about how
we have been working to rebuild confidence in railway
traffic and also in Rail Net Denmark as a company.
One of the next major achievements will have to do with
another remaining problem on the Danish railway – the
signalling and interlocking systems.
In 2006, Danish politicians made a principal decision
that the diverse signalling and interlocking systems on the
Danish rail net should be replaced by one system compliant
with the European ERTMS standard.
This decision was principal, because a more firm ground
is needed before a final decision on an investment of several
billion Euro can be taken. Repeating the framework from
the track project Rail Net Denmark is to provide this
fundament. This is being conducted within a project
programme with the task of providing a thorough
assessment of the feasibility and risks of a new system.
Problems with current signalling set up
A rise in the number of untraceable signal failure is the
most acute threat to punctuality. In current rail traffic, half
of all infrastructure related delays on the mainlines are due
to signalling.
www.europeanrailwayreview.com
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114 |
Page 115 |
Page 116