NORTHERN EUROPE PROFILE: RHK & VR-TRACK LTD
bridge and the portal of the Labbacka
tunnel took place outside the breeding
season for birds.
The construction of harbour traffic
channels produced approximately 300,000
cubic metres of soil and approximately
1,900,000 cubic metres of rock. This has
been used as fill in the harbour area and
in structural layers, noise barriers and
landscaping for traffic channels.
Harbour railway line
The harbour railway line will be 19km
long and have a single track that is
Figure 3: Organisation of the Harbour project
electrified (1*25 kV), blocked and
equipped with automatic train protection. length of 725 metres and a maximum Savio railway tunnel and run as much as
The line will only be used for freight weight of 4,500 tonnes. 60 metres below the surface in some
traffic, with a maximum axle load of 25 When the harbour goes into operation, places before resurfacing next to Ring
tonnes. It will initially handle 10 trains a the volume of traffic will be 5-6 trains a Road III (see Figure 6 on page 33).
day, five in each direction. This is day in each direction plus 3-4 additional After the Savio tunnel, the line will
expected to increase to a maximum of trains a week and even more at peak follow the same corridor as Ring Road III
16-20 trains a day. The line will have a periods. As a rule, trains will generally and the harbour road for approximately
maximum speed of 80km/h. Thanks to the arrive during the night and morning and 2km and then run under the Labbacka
long railway tunnel, rail traffic will not depart during the evening. Natura 2000 area in a second tunnel
disturb residents. The line will have no The harbour railway line will split off appromximately 0.7km long. Then it will
level crossings. The track will consist of from the main line in the Savio section of cross the Porvarinlahti railway bridge, in
60E1 rails on concrete sleepers and Kerava, approximately 25km from designing which special emphasis has been
ballast. Trains can have a maximum Helsinki. Here it will enter the 13.5km placed on noise abatement and water
Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116