Materials DuPont vFinal DR 18/12/08 12:18 Page 54
54
MATERIALS
2. Testing Kalrez 9100 parts in the harshest
possible conditions;
3. Extending testing well beyond timeframes
for planned maintenance to establish a new,
far reaching standard for PM limits, all with
Spansion process engineering agreement.
Currently, Kalrez 9100 continues to exceed the
normal Spansion PM schedule by up to 6 times
longer, extending the 30 day PM out to 180 days,
depending upon the seal location. Increased
equipment availability has increased the fab
production capacity by greater than 20%, without
additional equipment.
Tremendous value was realised by running
longer without planned maintenance shutdowns to
replace critical seals, Sorum reports. Kalrez 9100
parts performance is responsible for up to 6x
improvement in availability. Spansion has now
Above: Kalrez 9100 the key to a possible solution with a combination expanded their adoption Kalrez 9100 to other
test results table of innovative filler and crosslinking technology. As tools in both thin films and dry etch with
evident from the extensive evaluation run by consistently favourable results.
Spansion (see table above), the resulting product ‘From concept to commercialisation, the
exhibited significantly less seal erosion, reduced collaborative effort between Roger Sorum at
particle generation and better elastic recovery Spansion and our team made the difference,’
characteristics. The life expectancy of the critical according to Steve Metaxas, global semiconductor
parts improved. marketing manager, DPE. ‘Roger’s feedback and
After reviewing specifications and test results, shared effort resulted in a solution that exceeded
product modifications were made and parts were all our mutual expectations.’
“O-rings should not produced for trials against other competitive
be the limiting factor FFKM products. Kalrez 9100 parts outperformed
for bringing a tool the competitive FFKM products under all
down for conditions attempted.
preventative The DPE and Spansion team, working together,
maintenance,” pushed Kalrez 9100 parts to extreme parameters
claims Roger Sorum, faster than anyone expected,’ said Kevin
equipment engineer DeMartini, market development manager and
at Spansion applications engineer - DPE. ‘The exchange of
information was refreshing and contributory to the
success of this process.
Understanding results
Key learnings from the collaboration between
Spansion, as the customer with the problem, and
DPE, as the materials science expert, were the
following:
1. Active feedback during development in real FIG 1: Cross sectional view of a MESC flange
time; seal showing erosion due to plasma attack
After reviewing specifications and test results, product modifications
were made and parts were produced for trials against other
competitive FFKM products. Kalrez 9100 parts outperformed the
competitive FFKM products under all conditions
www.euroasiasemiconductor.com December 2008 / January 2009
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68