Feature 1 | repair and conversion
FPDSO conversion underway
A contract for the engineering of a one-of-a-kind FPDSO conversion has
been signed.
D
eltamarin and the Brazilian offshore
service company, Petroserv SA, have
signed an engineering contract for
the basic and detail engineering of an FPDSO,
called Dynamic Producer. The unit will be set
to work in Brazilian oilfields under a contract
from Petrobras once the conversion - of an
existing tanker - is complete.
This is the first contract that Deltamarin
has received in the Brazilian offshore
market and it is hoped it will strengthen the
company’s position in the FPSO market.
Offshore is currently a main focus area for Dynamic Producer is currently being converted. The detailed engineering was carried out
Deltamarin and its first newbuilding concept by deltamarin, of Finland.
developments are also in the pipeline.
This engineering project has a very tight
schedule and is to be completed within drilling derrick and moonpool on deck, at the head office in Raisio, where Petroserv
the first quarter of 2008. It is expected that making it an FPDSO. has also placed its own site team consisting of
the work will take approximately 70,000 The scope of the work includes all eight to 10 staff members.
engineering man-hours. disciplines, such as structural, machinery, This work is the second of this kind for
This is thought to be an unusual project, piping, HVAC, electrical, instrumentation, Deltamarin, after the Bluewater Aoka Mizu
as the existing ship was one of the very first architectural, and safety. The Deltamarin conversion, which is now being worked on
vessels to be designed as an FPSO with a project team has already started the work in Singapore. OMT
In situ repair reduces downtime costs
An FPSO repair recently carried out highlighted the versatility of SPS
Overlay.
S
teel repairs completed successfully have been prohibitive. were also injected to reinforce hull
onboard FPSO Conkouati off Instead, mobile injection equipment steelwork. OMT
the coast of Point Noire, in the was shipped to FPSO Conkouati whilst
Republic of Congo, has demonstrated the unit continued in normal operation.
the versatility of SPS Overlay as an on- A total of 616m² of SPS Overlay was
site repair medium. Originally a single- used to reinstate steelwork in various
hulled 232,918dwt VLCC built in 1973, areas of the hull. Four areas of side
FPSO Conkouati is owned by Perenco shell vulnerable to impact damage from
and deployed on the Yombo field, some fenders and offloading tankers were
60miles off the coast of Congo. strengthened on the unit’s port side by
Steel diminution over time had injecting 24 newly created cavities. A
meant that the offshore unit required further 124 cavities next to the hull in
steel reinforcement in various areas of No 5 port and starboard cargo tanks
the hull. However, the costs of halting
production at the offshore oil field
and taking the FPSO off station for The Fpso Conkouati was recently repaired
conventional repairs at a shipyard would using sps overlay.
14 Offshore Marine Technology 1st Quarter 2008
OMT 1stQ 08 - p14.indd 14 11/02/2008 11:46:15